top of page
Writer's pictureHawaiʻi State Senate

Hawai'i Island Lane Closures for the week of March 23-27


PLEASE NOTE: Lane closure schedules may change at any time without further notice.  All projects are weather permitting.


— HAWAII BELT ROAD (ROUTE 19) —


1) HONOMU

Closure of single lane at a time on Hawaii Belt Road (Route 19) in both directions between mile markers 14 and 16, Kolekole Bridge to Lepolino Bridge, on Monday, March 23, through Friday, March 27, from 7:30 a.m. to 2:30 p.m., for landscaping work. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


2) PAAUILO (24-HOUR WORK)

Closure of single lane at a time on Hawaii Belt Road (Route 19) in both directions in the vicinity of mile marker 38, Kaumoali Bridge, for guardrail installation work. Traffic flow in both directions will be directed with the use of temporary traffic signals.


3) PAAUILO

Closure of single lane at a time on Hawaii Belt Road (Route 19) in both directions in the vicinity of mile markers 35 and 39, East Paauilo Bridge to Kalopa Bridge, on Monday, March 16, through Friday, March 20, from 8 a.m. to 3:30 p.m., for guardrail work. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


4) PAAUILO

Closure of single lane at a time on Hawaii Belt Road (Route 19) in both directions in the vicinity of mile markers 34 and 36, Mauna Kea Ranch Road to Hauola Road, on Monday, March 23, through Friday, March 27, from 7:30 a.m. to 2:30 p.m., for landscaping work. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


--- KEAAU-PAHOA ROAD (ROUTE 130) ---


1) PAHOA

Closure of single lane at a time on Keaau-Pahoa Road (Route 130) in both directions between Ilima Street and Ainaloa Boulevard, on Monday, March 23, through Friday, March 27, from 8:30 a.m. to 3:00 p.m. for construction zone preparation for the Ainaloa Roundabout. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


--- MAMALAHOA HIGHWAY (ROUTE 11) ---


1) KAU

The Ninole and Hilea Stream Bridges on Mamalahoa Highway (Route 11) in the vicinity of Punaluu Black Sand Beach (Ninole Loop Rd.) are closed for bridge reconstruction work. Traffic will be detoured through the adjacent temporary bypass bridges for the duration of remaining construction operations.


2) KAU

Closure of single lane at a time on Mamalahoa Highway (Route 11) in both directions in the vicinity of mile markers 27 and 31, District of Kau Sign to Namakani Paio Campground, on Monday, March 23, through Friday, March 27, from 7:30 a.m. to 2:30 p.m. for landscaping work. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


3) KAU

Closure of single lane at a time on Mamalahoa Highway (Route 11) in both directions in the vicinity of mile markers 65 and 68, Ka’alualu Road to Kiola Ka’a Road, on Monday, March 23, through Friday, March 27, from 7:30 a.m. to 2:30 p.m., for landscaping work. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


4) NORTH KONA

Closure of single lane at a time on Mamalahoa Highway (Route 11) in both directions in the vicinity of mile markers 31 and 34, Hualalai Ranch Road to Akamai Street, on Monday, March 23, through Friday, March 27, from 7:30 a.m. to 2:30 p.m. for landscaping work. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


5) SOUTH KONA

Closure of single lane at a time on Mamalahoa Highway (Route 11) in both directions in the vicinity of mile markers 91 and 93, Kipahoehoe Natural Area Reserve to Ohia Malu Road, on Monday, March 23, through Friday, March 27, from 7:30 a.m. to 2:30 p.m., for landscaping work. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


--- AKONI PULE HIGHWAY (ROUTE 270) ---


1) NORTH KOHALA

Closure of single lane at a time on Akoni Pule Highway (Route 270) in both directions in the vicinity of Halaula-Maulili Road, on Monday, March 23, through Friday, March 27, from 8:30 a.m. to 3 p.m., for installation of waterlines. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


2) NORTH KOHALA

Closure of single lane at a time on Akoni Pule Highway (Route 270) in both directions between Iole Road to Akana Place, on Monday, March 23, through Friday, March 27, from 7:30 a.m. to 2:30 p.m., for installation of waterlines. Traffic flow in both directions will be maintained through alternating traffic control (contraflow).


bottom of page